Select Page

News

ELECTRICA PROJECT: SITE ACCEPTANCE TESTING COMPLETED

Cluj-Napoca, Romania – on the Electrica Nord Project, Site Acceptance Testing was completed for the Cluj Region. This testing was completed at the headquarters of Electrica Nord Transilvania, Cluj-Napoca, where the 3.6.1 ADMS system was delivered. In addition, DMS...

ARIZONA PUBLIC SERVICE: Phase 2 FAT Complete

Phoenix, ARIZONA PUBLIC SERVICE accepted “Phase 2 FAT Complete” milestone on 3.5.1 ADMS software version on Thursday, 12 October. The focus of the second phase of the APS project is the introduction of DSCADA functionality and basic DMS functions into daily...

CERTIFICATE OF COMPLIANCE

Knoxville -  The CIM standards are very robust, but without compliance and/or interoperability testing they are still open to interpretation. By aligning interpretations of the standard, utilities can get implementations from different vendors in a uniform way,...

BIHAR PROJECT: MILESTONE SAT COMPLETED

Bihar, India, MILESTONE SAT – On Friday, 8 September 2017, Indian company SBPDCL (South Bihar Power Distribution Company Limited) accepted the completion of SAT milestone on Bihar project. Successful closing of this milestone, which began on 28 August, is very...

UK INNOVATION SUMMIT 2017 – Schneider Electric DMS

On September 7, this year, London hosted the UK Innovation Summit. This event was attended by top leaders from energy sector from across the UK and Ireland, with the aim of promoting the latest technologies, trends, and innovations by which Schneider Electricproducts...

CARUNA PROJECT: SYSTEM FINAL ACCEPTANCE

Finland, PROJECT CARUNA, MILESTONE – System final acceptance. The last milestone, was accepted on 2 August 2017 which makes Schneider Electric’s ADMS the main system for controlling all network outages. This milestone represents the transition to Warranty period which...

ENWL PROJECT: SCADA GO LIVE

Manchester, UK - After availability period, ENWL Company officially entered SCADA Go Live phase on Wednesday, 24 August 2017. Connection with the ENWL Production Legacy SCADA system has been done through ICCP, with the 3.6.1. version of ADMS software. With the entry...